In response to safety concerns and worsening traffic conditions, TxDOT is planning to widen FM 2931 in Denton. The project is approximately 6.37 miles and will span from US 380 (East University Drive) to FM 428 (Spring Hill Road). The first phase of the project will transform the 2-lane road into a 4-lane, urban roadway and will include the construction of a 42-foot-wide raised median. Phase two will transform FM 2931 into a 6-lane roadway and will add a 3rd lane in each direction.
Approximately 46 acres of new ROW would be required to accommodate the proposed improvements. TxDOT is scheduled to begin Right-of-Way acquisitions in Fall 2021. Before ROW acquisitions can occur, however, TxDOT must still prepare a preliminary design and receive environmental clearance.