TxDOT is preparing for future population growth in Denton County with their most recent plans to improve State Loop 288. The project extends 9 miles from IH 35 W to IH 35. The final product of the SL 288 improvements will be a newly located, four-lane frontage road system. Improvements will be completed in two phases. Phase one includes the construction of one frontage road which will be a two-lane, two way street. Phase one also includes securing right of way and constructing a sidewalk and median. In Phase two, there will be construction of another two lane frontage road, and both two-lane frontage roads will become one-way frontage roads. In August 2020, the project’s Final Environmental Assessment was issued by TxDOT for public review. The next step for the project is the acquisition of approximately 414.7 acres of Right of Way.